Ohio Notice of Commencement on a Flip: When to Record It and the 60-Day Lien Window

November 22, 2026

By the ACC Solutions Team

Short answer: under Ohio Revised Code 1311.04, the owner who contracts for an improvement records a notice of commencement with the county recorder before any labor, work or materials that could lead to a mechanics' lien. On a flip, that owner is you or your LLC, so the notice belongs on the closing-to-demo checklist, not the contractor's. Subcontractors and suppliers on a one- or two-family house then have 60 days from their last day on the job to record a lien affidavit under 1311.06, and a flip doesn't get the pay-in-full protection Ohio gives owner-occupants. That's why we tell out-of-town investors to plan lien waivers before the final payment, not at closing.

This post is from the ACC Solutions Team. It summarizes Ohio Revised Code 1311.04, 1311.06 and 1311.011, and the Cuyahoga County Fiscal Officer's Transfer and Recording page, read November 21, 2026. It's general information, not legal advice. Ohio's mechanics' lien law has more steps than this post covers, so talk to an Ohio real estate attorney about a specific project.

What goes in an Ohio notice of commencement?

Section 1311.04(B) requires the notice in affidavit form, with:

  • The legal description of the property (the one in the deed you took title by is enough) and a brief description of the improvement.
  • The name, address and capacity of the owner contracting for the work, and of the owner's designee, if any.
  • The name and address of every original contractor. On a single- or double-family dwelling with more than one original contractor, the owner may instead state that multiple original contractors are involved.
  • The date the owner first signed a contract with an original contractor.
  • Every lender financing the improvement and every surety on a payment bond, if any.
  • The statutory notice "To Lien Claimants and Subsequent Purchasers," the preparer's name and address, and the expiration statement: four years from recording unless a different date is specified.
  • The owner's or agent's verifying affidavit.

The "multiple original contractors" option matters on flips. If you hire a roofer, an electrician and a general contractor separately on a double, you don't have to list each one; if you bring on a new lender or surety later, 1311.04(A)(2) says to amend the original notice.

Duties after it's recorded

DutyWhat 1311.04 says
Post itKeep a copy posted in a conspicuous place on the property during the physical work. (The posting exception is for home purchase contracts, which are for buyers who will live in the house.)
Give it to your contractorServe a copy on the original contractor, or you're liable for the contractor's expenses getting that information.
Answer requestsWithin 10 days of a written request from a subcontractor, supplier or laborer, serve them a copy.
Get it rightIncorrect information can make the owner liable for a lien claimant's lost lien rights and expenses, including attorney's fees, when they relied on it.

What happens if you never record one?

Under 1311.04(I), if the owner doesn't record the notice, a subcontractor's or supplier's deadline to serve a notice of furnishing is extended until 21 days after the notice is recorded, and they don't need to serve one to keep lien rights for the period before it is recorded. In plain terms, skipping the notice doesn't make liens go away; it takes away the early warning that notices of furnishing give you about who's working on your house.

The 60-day lien window and why it matters at resale

Section 1311.06(B) sets how long a lien claimant has to record a lien affidavit, counted from the last day they worked or delivered materials:

PropertyDeadline
One- or two-family dwelling, or a residential condo unit60 days
Liens under 1311.021120 days
Everything else75 days

On a fast flip, 60 days after the last trade leaves can overlap your listing and closing. A sub your general contractor didn't pay can still record a lien in that window.

Why paying your contractor in full isn't the end of it on a flip

Section 1311.011 says that under a "home construction contract," subcontractors and suppliers have no lien if the owner paid the original contractor in full before receiving a copy of a lien affidavit. But the definition only covers a dwelling "used or is intended to be used as a personal residence by the owner." A flip you plan to sell doesn't meet that definition, so don't count on that protection. Ask your attorney how to structure payments; collecting lien waivers from the contractor and major subs and suppliers before each draw is the step investors commonly ask about.

Our notice-of-commencement checklist for a flip

  1. Close, then record the notice before the first contractor or delivery shows up. Put it on the same list as utilities and insurance.
  2. Use the legal description from your deed, and if several trades are contracted separately on a single- or double-family house, use the "multiple original contractors" statement.
  3. Post a copy on site and give one to each original contractor.
  4. Keep a folder for written requests and answer within 10 days.
  5. Track each trade's last day on site and count 60 days forward before you plan the closing.
  6. Collect lien waivers with each payment, and put recording the notice in your holding costs. Cuyahoga's standard recording fee, effective October 24, 2024, is $39 for the first two pages and $8 for each page after; our post on Cuyahoga County recording fees has examples.

Hiring trades yourself? Read Ohio contractor license rules for flippers first. For the time side of the budget, see how to estimate flip holding costs.

Where the A.I. Deal Assistant fits

Before any of this, you need to know whether the house is worth buying. Paste an address or a Zillow link into our A.I. Deal Assistant and you get ARV from recent comps, a rehab estimate built on square-footage logic plus national and local cost data, projected flip profit and a property snapshot. The rehab number tells you roughly how much contractor money will be flowing, which is the money lien waivers protect. Results "are estimates to help you screen deals. They are not appraisals or inspections. Always confirm the numbers with your own due diligence."

See how the A.I. Deal Assistant works · Try 10 free deals

Flipping in Cleveland from another state or country? The ACC team coordinates rehabs in Cleveland and Cuyahoga County through our rehab project coordination service. We don't give legal advice or prepare recorded documents. We work asynchronously, so you can send a question by email or the contact form from any time zone.

ACC Solutions Team
Phone: (216) 238-5999 · Email: support@accmgmtsolutions.com · Contact form
6545 Market Ave N, Canton, OH 44721
We work asynchronously, so you can reach us by email or the contact form from any time zone; you don't need to catch us during Ohio business hours.

Frequently Asked Questions

Who records the notice of commencement in Ohio?

The owner, part owner or lessee who contracts for the improvement, under Ohio Revised Code 1311.04(A). On a flip, that is the investor or the investor's LLC, and it is recorded before labor, work or materials start.

How long is an Ohio notice of commencement good for?

The statutory statement says the notice expires four years from the date of recording unless a different date is specified in it.

How long does a contractor have to file a mechanics lien in Ohio?

Under Ohio Revised Code 1311.06(B), 60 days from the last labor or materials for a one- or two-family dwelling or residential condo unit, 120 days for liens under 1311.021, and 75 days for other property.

What happens if I don't record a notice of commencement?

Under 1311.04(I), subcontractors' and suppliers' deadline to serve a notice of furnishing is extended until 21 days after the notice is recorded, and they keep lien rights for work before it is recorded without serving one.

Does paying my contractor in full protect a flip from subcontractor liens in Ohio?

Ohio's pay-in-full protection in 1311.011 applies to home construction contracts for a dwelling the owner uses or intends to use as a personal residence. A flip held for resale doesn't fit that definition; ask an Ohio attorney about lien waivers and payment structure.

Back to Blog