Key findings
- Our example rental turn cart of basics costs about 10% more than last winter: about $1,810 then, about $2,000 now.
- Copper wire led the increases. A 250 ft roll of 12/2 went from $149 to $179 (+20%), and the federal copper wire and cable index rose 25.5% in a year.
- Shelf prices are outrunning factory prices. A 1/2 in. drywall sheet rose 13% on our receipts while the federal gypsum index rose 0.9%. Not everything is up: OSB sheathing fell 13%.
If you priced a rental turn last winter, the materials line in that budget is already short. The cart of basics we use as a benchmark (drywall, mud, paint, primer, wire, pipe, studs, one exterior door and trash bags) cost about $1,810 on the shelf last winter. The same cart costs about $2,000 today. That is about $190 more for the same items, before tax, and paint and copper wire alone account for about 60% of the increase.
ACC Solutions Team manages rentals and coordinates rehabs across Greater Cleveland, so we see shelf prices every time a job needs materials. For this report we matched the exact same products on our receipts from late 2025 against our latest 2026 purchase, then checked the results against federal producer price data and The Home Depot's latest public results. The short version: materials cost about 7% more overall, the increases are concentrated in a few categories, and a handful of items got cheaper.

What the same items cost now
Across every item we bought both in late 2025 and again in 2026, shelf prices rose about 7%, weighted by how much of each item we buy. The typical item rose about 5%. About 6 in 10 items went up, about 1 in 5 held flat, and about 1 in 5 got cheaper.

| Item | Then | Now | Change |
|---|---|---|---|
| 2x4x10 framing stud | $4.65 Dec 2025 | $5.72 Sep 2026 | +23% |
| 14/2 copper electrical wire, 250 ft roll | $102.60 Sep 2025 | $124.50 Oct 2026 | +21% |
| 3/4 in. PEX-A water pipe, 20 ft | $14.96 Sep 2025 | $17.98 Aug 2026 | +20% |
| 12/2 copper electrical wire, 250 ft roll | $149.00 Dec 2025 | $179.00 Oct 2026 | +20% |
| 12/2 copper electrical wire, 1,000 ft roll | $499.00 Dec 2025 | $599.00 Sep 2026 | +20% |
| 4 in. PVC drain pipe, 10 ft | $26.91 Dec 2025 | $30.96 Sep 2026 | +15% |
| 1/2 in. lightweight drywall, 4x8 sheet | $12.98 Nov 2025 | $14.70 Oct 2026 | +13% |
| 1/2 in. PEX ball valve | $8.98 Dec 2025 | $9.98 Aug 2026 | +11% |
| Contractor trash bags, 50 ct | $29.97 Dec 2025 | $32.97 Nov 2026 | +10% |
| 5 gal. interior paint and primer, satin | $167.00 Nov 2025 | $182.00 Nov 2026 | +9% |
| 4.5 gal. all-purpose joint compound | $21.78 Oct 2025 | $22.94 Oct 2026 | +5% |
| 1/2 in. mold-resistant drywall, 4x8 sheet | $21.48 Nov 2025 | $22.46 Oct 2026 | +5% |
| 32 in. steel prehung exterior door | $265.00 Dec 2025 | $275.00 Jul 2026 | +4% |
| 5 gal. stain-blocking primer | $99.00 Nov 2025 | $99.00 Oct 2026 | 0% |
| 1/4 in. drywall, 4x8 sheet | $16.48 Nov 2025 | $15.58 Oct 2026 | -6% |
| 1/2 in. OSB sheathing, 4x8 | $15.48 Nov 2025 | $13.43 Nov 2026 | -13% |
Shelf prices from ACC Solutions Team purchase records, Cleveland area. Sales tax excluded. Month of each price shown under it.
Three patterns stand out. First, copper wire did not jump once. The 250 ft roll of 12/2 we run in kitchens and baths went from $149 in December 2025 to $159 in January, $164 in February and March, and $179 from April on. Second, lumber is volatile rather than simply higher: the 2x4x10 stud was $5.38 in September 2025, fell to $4.65 that December and reached $5.72 this September, while 1/2 in. OSB dropped from $15.48 to as low as $8.98 this spring and is back at $13.43. Third, plumbing moved together: PEX pipe, PEX valves and PVC drain pipe all rose between 11% and 20%.
Shelf prices vs. factory prices
The federal producer price index (PPI) tracks what U.S. manufacturers receive. It is not a store price. Comparing the two shows where the shelf is running ahead of the factory.

Drywall is the clearest case. The 1/2 in. sheet on our receipts rose 13% from November 2025 to October 2026, while the federal index for gypsum products rose 0.9% from October 2025 to October 2026. Part of that gap is timing, since the same sheet cost $14.02 in early fall 2025 before dipping to $12.98. Paint shows the same pattern at a smaller scale: up 9% on the shelf against 3.8% for the federal paint index. Copper wire runs the other way. The federal copper wire and cable index rose 25.5% in a year, faster than the 20% we saw on the shelf. Wire is the one staple where the factory index is still ahead of the shelf, so it is the item we are watching most closely.
The national picture
Federal producer prices for goods used in residential construction rose 9.8% from October 2025 to October 2026. Excluding energy, building material prices rose 5.8%, according to NAHB's November 16 analysis of the same data. For comparison, consumer prices overall rose 3.7% in the 12 months ending September 2026, according to the Bureau of Labor Statistics.
| Material (BLS PPI) | Series ID | 1 year | 2 years |
|---|---|---|---|
| Copper wire and cable | WPU10260314 | +25.5% | +42.9% |
| Plywood | WPU083 | +16.9% | +15.8% |
| Softwood lumber | WPU0811 | +10.6% | +6.6% |
| Inputs to residential construction, goods | WPUIP2311001 | +9.8% | +12.9% |
| Plastic pipe fittings and unions | WPU07210604 | +8.8% | +11.8% |
| Metal doors, sash and trim | WPU1071 | +7.3% | +19.8% |
| Plumbing fixtures and fittings | WPU105 | +6.0% | +11.9% |
| Insulation materials | WPU1392 | +4.6% | +3.4% |
| Builders' hardware | WPU104101 | +4.4% | +14.1% |
| Prepared paint | WPU0621 | +3.8% | +7.0% |
| Plastics pipe | WPU07210603 | +3.8% | -2.5% |
| Ready-mix concrete | WPU1333 | +2.4% | +2.5% |
| Asphalt roofing and siding | WPU1361 | +2.3% | +2.0% |
| Resilient (vinyl) floor coverings | WPU1232 | +1.3% | +1.9% |
| Gypsum products (drywall) | WPU137 | +0.9% | +1.9% |
| Household appliances | WPU124 | -0.4% | +2.2% |
1 year: October 2025 to October 2026. 2 years: October 2024 to October 2026. Not seasonally adjusted. October 2026 values are preliminary and may be revised for four months. Source: U.S. Bureau of Labor Statistics, read November 18, 2026.
Why prices are up
The Associated General Contractors of America (AGC) lists 50% tariffs on items made mostly of steel, aluminum or copper, 25% on products made substantially of those metals, a 10% tariff on softwood lumber and timber on top of existing softwood lumber duties (currently 14%), and 50% tariffs on specific goods from Canada including paint, caulking compounds and vinyl flooring (AGC Tariff Resource Center, updated November 2, 2026). Fuel and freight add to it: AGC reports diesel up 115.2% and truck freight up 24.6% from October 2025 to October 2026 (AGC, November 13, 2026).
What the retail side reports
The Home Depot reported a third quarter fiscal 2026 average ticket of $93.09, up 3.0% from $90.39 a year earlier, while comparable customer transactions fell 0.5% (company release, November 17, 2026). Shoppers are spending more per trip and making slightly fewer trips.
The rental turn cart, line by line
To make the numbers concrete, we priced an illustrative cart for a typical 1,000 sq ft rental turn: patch and repaint, some plumbing and wiring repair, and one exterior door. The quantities are an example, not a specific job. The prices are our actual shelf prices then and now.
| Item | Qty | Then | Now |
|---|---|---|---|
| 1/2 in. lightweight drywall, 4x8 | 10 | $129.80 | $147.00 |
| 1/2 in. mold-resistant drywall, 4x8 | 4 | $85.92 | $89.84 |
| All-purpose joint compound, 4.5 gal. | 2 | $43.56 | $45.88 |
| Interior paint and primer, 5 gal. | 4 | $668.00 | $728.00 |
| Stain-blocking primer, 5 gal. | 1 | $99.00 | $99.00 |
| 12/2 copper wire, 250 ft roll | 1 | $149.00 | $179.00 |
| 14/2 copper wire, 250 ft roll | 1 | $102.60 | $124.50 |
| 4 in. PVC drain pipe, 10 ft | 2 | $53.82 | $61.92 |
| 3/4 in. PEX-A pipe, 20 ft | 3 | $44.88 | $53.94 |
| 1/2 in. PEX ball valve | 4 | $35.92 | $39.92 |
| 2x4x10 framing stud | 10 | $46.50 | $57.20 |
| 32 in. steel prehung exterior door | 1 | $265.00 | $275.00 |
| Contractor trash bags, 50 ct | 3 | $89.91 | $98.91 |
| Total, before tax | $1,813.91 | $2,000.11 |
Illustrative cart. Then: late 2025 shelf price. Now: latest 2026 shelf price. Difference $186.20, or 10.3%. Excludes flooring, cabinets, appliances and fixtures.
Of the $186.20 increase, the four buckets of interior paint add $60.00 and the two rolls of copper wire add $51.90. Everything else adds about $74 combined.
What this means for you
Landlords and buy-and-hold investors
If your turn budgets still use last winter's prices, the materials line is likely about 10% light, based on our example cart. Electrical and plumbing repairs carry the biggest jumps, so price those first, and recheck reserves for units turning over this winter.
Flippers
Rerun your rehab budget at today's prices before you make an offer, not after. Our fix and flip analyzer lets you test the margin with an updated materials number. Buy framing close to when you need it, because lumber has swung both ways this year.
Out-of-state and international buyers
Ask for itemized material quotes with a date on them. A scope priced six months ago may not hold for copper, plumbing or anything affected by tariffs. Our guide to investing in Cleveland from out of state covers how to manage a rehab you cannot visit every week.
Contractors
Copper wire rose in three steps between January and April, so keep material quote windows short. For larger jobs, AGC points contractors to price escalation clauses such as the ConsensusDocs 200.1 Material Price Escalation Amendment. On wire, roll size matters: 12/2 costs about $0.60 per foot in a 1,000 ft roll ($599) vs about $0.72 per foot in a 250 ft roll ($179), and 14/2 about $0.42 vs $0.50.
- Same items: each comparison uses the identical product (same product number) on ACC Solutions Team purchase records in the Cleveland area.
- Shelf price: the listed price before any account pricing, so it reflects what any shopper would see. Sales tax excluded.
- Time gaps: "then" is a late 2025 purchase (September to December 2025); "now" is the latest 2026 purchase (July to November 2026). Gaps run 7 to 13 months, so we say "about a year," not an exact 12 month change.
- Overall change: about 7% is the average change across all items bought in both periods, weighted by how much of each item we buy. As a cross check, weighting the federal producer price changes by our own category mix also gives about 7%, or about 5% excluding copper wire.
- Example cart: the rental turn cart is illustrative. Quantities are an example for a typical 1,000 sq ft turn, not a real job.
- Federal data: BLS Producer Price Index, not seasonally adjusted, October 2025 vs October 2026 (October 2026 preliminary). Series: WPU10260314, WPU1026, WPU083, WPU0811, WPUIP2311001, WPU07210604, WPU07210603, WPU1071, WPU105, WPU1392, WPU104101, WPU0621, WPU1333, WPU1361, WPU1232, WPU137, WPU124. Read November 18, 2026.
- Limits: one metro area, one buyer's records. Store prices vary by location and date. This is general information, not investment, tax or legal advice. ACC is not a real estate brokerage, law firm or qualified intermediary.
What we are watching for December
Copper wire, since the federal index is still running ahead of the shelf. Plywood, up 16.9% at the producer level, while the OSB on our receipts got cheaper. Paint and vinyl flooring, both on AGC's list of Canadian goods facing 50% tariffs. And the next federal producer price release.
Next update: December 2026.
Planning a rehab or rental turn in Cleveland and want a budget built on current prices? Talk to ACC Solutions Team about rehab project coordination.
Call (216) 238-5999Frequently asked questions
How much have rehab material prices gone up in Cleveland in the past year?
On our own purchase records, the same rehab materials cost about 7% more than about a year ago, and our example rental turn cart costs about 10% more than last winter. Nationally, federal producer prices for goods used in residential construction rose 9.8% from October 2025 to October 2026, according to the Bureau of Labor Statistics.
Which rehab materials went up the most?
Copper electrical wire, plastic plumbing pipe and framing lumber rose the most on our receipts, each up 15% to 23%. A 250 ft roll of 12/2 copper wire went from $149 to $179. The federal producer price index for copper wire and cable rose 25.5% from October 2025 to October 2026.
Did any building materials get cheaper?
Yes. On our receipts, 1/2 in. OSB sheathing was about 13% cheaper than last November and 1/4 in. drywall about 6% cheaper. A 5 gallon bucket of stain-blocking primer cost the same as a year ago.
Why is drywall up 13% on the shelf when the factory index barely moved?
The federal producer price index measures what U.S. manufacturers receive, not what a store charges. The index for gypsum products rose 0.9% from October 2025 to October 2026, while the shelf price of the 1/2 in. drywall sheet on our receipts rose 13% from November 2025 to October 2026. Part of the gap is timing: that sheet cost $14.02 in early fall 2025 before it dipped to $12.98.
Why are building materials more expensive in 2026?
The Associated General Contractors of America points to tariffs of up to 50% on steel, aluminum and copper products, a 10% tariff on softwood lumber on top of existing duties, and much higher diesel and freight costs. NAHB reports that building material prices excluding energy were up 5.8% from October 2025 to October 2026.
Sources
- ACC Solutions Team purchase records, Cleveland area: same item shelf prices, late 2025 vs. 2026.
- U.S. Bureau of Labor Statistics, Producer Price Index, series pages: WPU10260314, WPUIP2311001, WPU137, WPU0621, WPU0811, WPU07210603, and the other series in the table above. Read November 18, 2026.
- U.S. Bureau of Labor Statistics, CPI-U 12 month change, Table 5, October 2026 release.
- NAHB, Building Material Prices 10% Higher than a Year Ago, November 16, 2026.
- AGC, Construction Input Costs Rise 13.3% From October 2025 to October 2026, November 13, 2026.
- AGC, Tariff Resource Center for Contractors, updated November 2, 2026.
- The Home Depot, Third Quarter Fiscal 2026 Results, November 17, 2026.
Cleveland Rehab Materials Price Watch is published monthly by ACC Solutions Team.